Facility Improvements

HHS Roof

Hanford High Roof Replacement

  • Cost: TBD
  • Completion Date: Fall 2024
  • Project Team: Siefken & Sons Construction
  • Details: Replacement of metal flashing and insulation, and full replacement of all flat roof membranes at Hanford High School. Including the original asphalt roof system on the gyms, library and auditorium roofs that did not get replaced during renovations in 2007.
Lynx Campus

1219 Thayer Drive Building Remodel

  • Cost: $265,300
  • Completion Date: 90% as of March 2023
  • Project Team: CKJT Architects and G2 Construction
  • Details: In September 2021 RSD purchased a two-story former church on the corner of Thayer Drive and Williams Boulevard. It was remodeled to enable it to function as additional instructional space for Three Rivers HomeLink, with the plan to have it serve as flexible space for other schools and programs in the future.
Greenhouse

Richland High School Greenhouse

  • Cost: $407,600
  • Completion Date: August 2023
  • Project Team: PBS Engineering and MH Construction
  • Details: A 1,500 square foot greenhouse is being constructed at Richland High School. The new greenhouse was built in the existing parking area of the auto shop and will be used for agriculture classes.

Contact

Brad Anderson
Facilities & Operations Assistant Director
509-967-6127
Bradley.Anderson@rsd.edu