In March 2017, the Richland School District selected Design West to be the architectural firm for the new Teaching Learning Administration Center (TLAC). The TLAC will be built on land adjacent to Leona Libby Middle School. The TLAC will be 41,000 square feet in size. Listed below is the project timeline.

 

Phase Timeline Status
Educational specifications May '17 - February '18 Done
Schematic design March - April '18 Done
Design development May - June '18 Done
Construction documents prepared July - December '18
Project goes to bid February '19
Construction begins March '19
TLAC opens January '20