Phase Timeline Status
Educational specifications May-July '03 Done
Schematic design July '03 - January '04 Done
Value engineering studies Jan.-Feb. '04 Done
Construction documents prepared March-Nov. '04 Done
Project goes to bid Nov.-Dec. '04 Done
Renovation begins February '05 Done
Renovation complete July '08  