Tapteal Elementary School

In March 2017, the Richland School District selected Design West to be the architectural firm for the new Tapteal Elementary School. The new Tapteal will be 65,000 square feet in size and house approximately 550 students. The new Tapteal will be built in the same location as the existing school; this means that Tapteal students will be displaced to Elementary School #11 for the 2019-20 school year. Fowler General Construction was selected to build the new school. Listed below is the project timeline.

 

Phase Timeline Status
Educational specifications February - March '18 Done
Schematic design April - May '18 Done
Design development June - August '18 Done
Construction documents prepared Sept '18 - January '19 Done
Project goes to bid March '19 Done
Construction begins June '19
School opens August '20