In June 2014, the Richland School Board selected Design West, Kennewick, to be the architectural firm for the new middle school construction project. The District's fourth middle school will be approximately 108,000 square feet in size and house 800 students. The school will be built on a 30-acre site in West Richland near the intersection of Keene Road and Belmont Boulevard. Listed below is the project timeline.

  

Phase Timline Status
Educational specifications July - August -14   Done
Schematic design  August - November '14   Done
Design development November '14 - March '15   Done
Construction documents prepared March - September '15   Done
Project goes to bid  January '16  Done
Construction begins  February '16   Done
School opens August '17   

 

 

New Middle School Construction
Click to zoom
November 3, 2016
Click to zoom
October 28, 2016
Click to zoom
October 28, 2016
Click to zoom
October 11, 2016
Click to zoom
September 27, 2016
Click to zoom
September 7, 2016