Richland School District       http://www.rsd.edu
art photo RHS summer art 3 RHS summer art 4 Swetha
 
saci ground clay goats Carri Rose violin boy RHS summer art 2 orchestra

Chief Joseph HVAC

In May 2013, the Richland School Board selected ALSC Architects and MSI Mechanical Engineers as the firms responsible for replacing the current HVAC roof top units with a more efficient boiler/chiller system. Listed below is the project timeline.

Phase Timeline Status
Schematic design May – June '13  Done
Design development   June – July '13  Done
Construction documents prepared July – October '13  Done
Project goes to bid    October '13  Done
Construction begins  April '14  Done
Construction completed  August '14  

  

Chief Joseph HVAC Upgrades
Click to zoom
August 5, 2014
Click to zoom
July 23, 2014
Click to zoom
July 23, 2014
Click to zoom
July 23, 2014
Click to zoom
July 16, 2014
Click to zoom
June 18, 2014
Click to zoom
June 12, 2014
Click to zoom
June 4, 2014
Click to zoom
May 27, 2014
Click to zoom
May 7, 2014
Click to zoom
April 30, 2014
Click to zoom
April 23, 2014
Click to zoom
April 16, 2014
Click to zoom
April 16, 2014
Click to zoom
April 7, 2014

Chief Joseph construction bid awarded

The Richland School District on November 26, 2013, awarded the general contractor bid for the Chief Joseph Middle School HVAC Upgrades Project to TW Clark Construction, Spokane. The bid of $3.02 million was the lowest of five bids submitted. Construction work is expected to begin in April 2014 and be completed by August 2014. The existing HVAC roof top units are being replaced with a more efficient boiler/chiller system.

“TW Clark Construction has an excellent reputation for completing projects on time and within budget,” says Kevin Knodel, Executive Director of Capital Projects. “The Chief Joseph project is in good hands.”

TW Clark Construction has completed a number of school construction/renovation projects in the region including:

  • Cottonwood Elementary School, Kennewick School District
  • Wahitis Elementary School, Othello School District
  • Transportation Center, Walla Walla School District

District residents approved a bond issue for the Chief Joseph upgrade and eight other projects in February 2013.